Collaboration par excellence

Example: Hasselt City Hall, Belgium — The building of the new municipal administration center in Hasselt, Belgium, demonstrates how seamless collaboration in building projects can minimize risks and save costs from the design phase all the way to commissioning.
A joint project of several brands of the Nemetschek Group.
Nemetschek brands involved: Allplan, GRAPHISOFT, Solibri

Pioneering planning and project execution with Open BIM

“The end-to-end use of BIM solutions constitutes genuine added value for all stakeholders in the building process
because it enables seamless and efficient collboration”

Steven Hendrickx, Head Architect in Hasselt

Large-scale, highly complex building projects in particular require ongoing, reliable and efficient coodination between all stakeholders – both internal and external – across disciplines and between companies. Therefore, in association with other market players, the Nemetschek Group is promoting the Open BIM data standard. This is a universal, collaborative approach to designing, constructing and operating buildings based on open standards and workflows It makes it possible for project stakeholders to collaborate, even if the type of software varies from user to user. The Industry Foundation Classes (IFC) interface has established itself as an open standard and is therefore of central significance.

Sharing and evaluating data throughout the entire product life cycle saves time and money and improves quality. The administration of data is key to this digital transformation, for it is only possible to take full advantage of the potential if each stakeholder can access the data that he or she needs at any given time. This begins with a realistic BIM building model, which is an essential prerequisite for a genuine 5D workflo. This model is no longer limited to just 3D construction data; it also includes data concerning the dimensions of time and costs.

Seamless collaboration exemplified by the Hasselt City Hall

Under the management of the architect team comprising Jaspers-Eyers, MASS Architects and Michel Janssen, a new municipal administration center is being built in Hasselt. The complex, consisting of a renovated building section and a new building, provides approx. 17,000 m2 for the city administration and social services as well as offices. The architects and their most important partners are using Open BIM software solutions for the entire construction process. Three Nemetschek solutions are being implemented for this project: Archicad from Graphisoft for the design and planning of the architects, Allplan Engineering for civil engineering, and the Solibri Model Checker for the BIM quality control carried out by the construction company.

From the beginning, all information concerning the building project is contained in the digital building model – from the draft to implementation – including all design details, desired materials, fire protection requirements, acoustic properties, insulation and building structures, and administration. This constitutes considerable added value for all stakeholders compared to the old standard model, which was purely 3D. Thus, this improvement ensures more than just seamless collaboration between all those involved. The complex project can be turned over to the municipality – the proud building owner – with the required quality, on time and within the specified budget.

Hasselt City Hall is groundbreaking – in terms of design, planning and project implementation.

Independent and yet consistent

Steven Hendrickx, the head architect in Hasselt, recognized four decisive factors with Open BIM over the course of the successful project:

  • Individual partners design their model with their preferred BIM software, and with their own templates. Outstanding collaboration is ensured, though, thanks to a common, uniform standard which is specified in advance.
  • The division of labor is defined at the beginning of the project. Data on statics, for instance, have an essential impact on the architecture and structural design. Data on heating, ventilation and air-conditioning, on the other hand, are also important but don’t generally flow directly into the architecture. These data, for example, can be sufficiently analyzed with the BIM solution for quality assurance from Solibri.
  • Design changes in one area don’t necessarily affect the plans of all the others involved in the project. The architecture and the building stage are inherently the most closely linked.
  • The expertise of the staff, i.e., extensive holistic knowledge of the various building disciplines, is also critical for the success of the project.

Two examples of the advantage of precise planning

In Hasselt, the construction company was commissioned with excavation, among other tasks. An assessment of the amount of sand that needed to be removed was done based on a cal culation using conventional 2D planning methods, which yielded a result of 800 cubic meters. The engineers used the Solibri Model Checker based on Open BIM and the data provided by the architects and arrived at a figue that was just half this amount, i.e., 400 cubic meters of sand. This shows how exact the work with Open BIM solutions can be.

The steel struts to be installed are another example: With the interface function IFC Exports from Allplan, it was possible to use the BIM model to automatically calculate which steel struts needed fieproofing. All it took was a mouse click to obtain precise results, right down to the running meter. In projects that don’t use Open BIM solutions, these calculations are made by manually entering the data from 2D drawings in Excel or some other software and then recalculating and evaluating the data for use in quotations and planning, a process that is susceptible to error and one that leaves a lot of room for interpretation. These errors often go undetected until the actual cost planning is already completed. In the case of the Hasselt City Hall,  it was possible to avoid such errors from the outset.

Converting to Open BIM pays off

As is the case with any change, it takes a certain amount of time for companies and employees to accept BIM as the norm. The best way, according to Steven Hendrickx, is to start out by planning smaller projects using BIM. The experience thereby gained will make it possible to complete successively larger BIM projects. The advantages of collaborating through Open BIM are obvious: The entire workflow is much simpler for all project stakeholders, and building projects are completed within time and cost budgets.

CONCLUSION

Consistent standards and open interfaces in par-ticular are essential for successful building projects. Stakeholders need solutions that can “work together” for all and any individual tasks being performed. Seamless collaboration between humans and machines: This is ensured with Open BIM, and backed by the brands of the Nemetschek Group.



Reference projects on this topic:

Allplan receives IFC2x3 CV2.0 Certification from buildingSMART for excellent IFC export

 

Munich, March 21, 2013 – The international association buildingSMART has extensively tested and recertified the BIM solution Nemetschek Allplan with respect to the IFC export – and hereby recognizes the company’s support of the Open BIM process. Thus Allplan is one of four products in the AEC market, which received this award at the international buildingSMART meeting in Waltham, USA, on March 12, 2013.

Aleš Široký, Technical Director at Nemetschek Allplan said: "This certification is an important step towards improving open BIM collaboration among our customers and their partners. Nemetschek Allplan is committed to IFC as the industry standard and our developers cooperate with other industry players so that we stay at the leading edge of open BIM exchange."

The Industry Foundation Classes (IFC) are an open standard for digital descriptions of building models. Shown are the logical building structures (e.g. Window-Opening-Wall-Story-Building), associated properties (attributes), and optional geometry. This allows, among other things the interchange of complex 3D design data with components and descriptive attributes between different construction software systems.

Building Smart is an international, cross-industry alliance dedicated to improving the efficiency and cost-effectiveness of the design, construction and facilities management industries, with an emphasis on information sharing and BIM. It has developed the open IFC standard (Industry Foundation Classes), also known as the buildingSMART Data Model.

In 2010, buildingSMART relaunched its certification scheme, introducing a clear distinction between import and export functions and improving quality checks. The scheme uses a web application, the Global Testing and Documentation Server (GTDS), which provides automated online testing of IFC files, tools for documentation of manual tests and is a place where candidates for certification can run tests to ascertain compliance. The database of GTDS stores all test results and provides test reports. Certification 2.0 by buildingSMART is open to all software developers who are members of buildingSMART.

Rasso Steinmann, who leads buildingSMART Implementer Support Group, said: "Our certification is a stringent process and buildingSMART congratulates the successful vendors. The number of test actions to date is over 1,400 – an indication of how seriously we take the process."

In addition to Allplan, the products ArchiCAD, Revit Architecture and Scia Engineer were also tested and certified. This means, three out of four successfully tested software solutions are from the Nemetschek AG. A clear commitment of the Nemetschek Group to Open BIM strategy.