Collaboration par excellence

Example: Hasselt City Hall, Belgium — The building of the new municipal administration center in Hasselt, Belgium, demonstrates how seamless collaboration in building projects can minimize risks and save costs from the design phase all the way to commissioning.
A joint project of several brands of the Nemetschek Group.
Nemetschek brands involved: Allplan, GRAPHISOFT, Solibri

Pioneering planning and project execution with Open BIM

“The end-to-end use of BIM solutions constitutes genuine added value for all stakeholders in the building process
because it enables seamless and efficient collboration”

Steven Hendrickx, Head Architect in Hasselt

Large-scale, highly complex building projects in particular require ongoing, reliable and efficient coodination between all stakeholders – both internal and external – across disciplines and between companies. Therefore, in association with other market players, the Nemetschek Group is promoting the Open BIM data standard. This is a universal, collaborative approach to designing, constructing and operating buildings based on open standards and workflows It makes it possible for project stakeholders to collaborate, even if the type of software varies from user to user. The Industry Foundation Classes (IFC) interface has established itself as an open standard and is therefore of central significance.

Sharing and evaluating data throughout the entire product life cycle saves time and money and improves quality. The administration of data is key to this digital transformation, for it is only possible to take full advantage of the potential if each stakeholder can access the data that he or she needs at any given time. This begins with a realistic BIM building model, which is an essential prerequisite for a genuine 5D workflo. This model is no longer limited to just 3D construction data; it also includes data concerning the dimensions of time and costs.

Seamless collaboration exemplified by the Hasselt City Hall

Under the management of the architect team comprising Jaspers-Eyers, MASS Architects and Michel Janssen, a new municipal administration center is being built in Hasselt. The complex, consisting of a renovated building section and a new building, provides approx. 17,000 m2 for the city administration and social services as well as offices. The architects and their most important partners are using Open BIM software solutions for the entire construction process. Three Nemetschek solutions are being implemented for this project: Archicad from Graphisoft for the design and planning of the architects, Allplan Engineering for civil engineering, and the Solibri Model Checker for the BIM quality control carried out by the construction company.

From the beginning, all information concerning the building project is contained in the digital building model – from the draft to implementation – including all design details, desired materials, fire protection requirements, acoustic properties, insulation and building structures, and administration. This constitutes considerable added value for all stakeholders compared to the old standard model, which was purely 3D. Thus, this improvement ensures more than just seamless collaboration between all those involved. The complex project can be turned over to the municipality – the proud building owner – with the required quality, on time and within the specified budget.

Hasselt City Hall is groundbreaking – in terms of design, planning and project implementation.

Independent and yet consistent

Steven Hendrickx, the head architect in Hasselt, recognized four decisive factors with Open BIM over the course of the successful project:

  • Individual partners design their model with their preferred BIM software, and with their own templates. Outstanding collaboration is ensured, though, thanks to a common, uniform standard which is specified in advance.
  • The division of labor is defined at the beginning of the project. Data on statics, for instance, have an essential impact on the architecture and structural design. Data on heating, ventilation and air-conditioning, on the other hand, are also important but don’t generally flow directly into the architecture. These data, for example, can be sufficiently analyzed with the BIM solution for quality assurance from Solibri.
  • Design changes in one area don’t necessarily affect the plans of all the others involved in the project. The architecture and the building stage are inherently the most closely linked.
  • The expertise of the staff, i.e., extensive holistic knowledge of the various building disciplines, is also critical for the success of the project.

Two examples of the advantage of precise planning

In Hasselt, the construction company was commissioned with excavation, among other tasks. An assessment of the amount of sand that needed to be removed was done based on a cal culation using conventional 2D planning methods, which yielded a result of 800 cubic meters. The engineers used the Solibri Model Checker based on Open BIM and the data provided by the architects and arrived at a figue that was just half this amount, i.e., 400 cubic meters of sand. This shows how exact the work with Open BIM solutions can be.

The steel struts to be installed are another example: With the interface function IFC Exports from Allplan, it was possible to use the BIM model to automatically calculate which steel struts needed fieproofing. All it took was a mouse click to obtain precise results, right down to the running meter. In projects that don’t use Open BIM solutions, these calculations are made by manually entering the data from 2D drawings in Excel or some other software and then recalculating and evaluating the data for use in quotations and planning, a process that is susceptible to error and one that leaves a lot of room for interpretation. These errors often go undetected until the actual cost planning is already completed. In the case of the Hasselt City Hall,  it was possible to avoid such errors from the outset.

Converting to Open BIM pays off

As is the case with any change, it takes a certain amount of time for companies and employees to accept BIM as the norm. The best way, according to Steven Hendrickx, is to start out by planning smaller projects using BIM. The experience thereby gained will make it possible to complete successively larger BIM projects. The advantages of collaborating through Open BIM are obvious: The entire workflow is much simpler for all project stakeholders, and building projects are completed within time and cost budgets.

CONCLUSION

Consistent standards and open interfaces in par-ticular are essential for successful building projects. Stakeholders need solutions that can “work together” for all and any individual tasks being performed. Seamless collaboration between humans and machines: This is ensured with Open BIM, and backed by the brands of the Nemetschek Group.



Reference projects on this topic:

DDS-CAD Security: Neue Planungslösung für Sicherheitstechnik auf dem Markt (German)

Der offizielle Startschuss für das Produkt zur Projektierung der elektronischen Sicherheitstechnik fällt auf der light+building in Frankfurt am Main. Neben DDS-CAD 13, der Open-BIM-Software für die Gebäudetechnik, präsentiert Hersteller Data Design System (DDS) den Planern der elektronischen Sicherheitstechnik mit DDS-CAD Security eine maßgeschneiderte Lösung für ihren Fachbereich.

Ascheberg, 09. März 2018 – Nils Kverneland, Geschäftsführer von DDS, erklärt: „Wir stellen immer öfter fest, dass unsere Anwender die Sicherheitstechnik von Beginn an in ihre Projektierung von Gebäudetechnik integrieren. Der Bedarf an richtlinienkonformer Planung von Sicherheitstechnik ist erheblich gestiegen. Der Schritt zu einem eigenständigen Softwareprodukt lag daher für uns nahe. DDS-CAD Security bietet den Planern viele nützliche Basisfunktionen des gewerkeübergreifenden Hauptproduktes DDS-CAD und ist gleichzeitig genau auf die Ansprüche der Sicherheitstechnik abgestimmt. Bei Bedarf können zusätzliche Module für Blitzschutz oder Flucht- und Rettungspläne ausgewählt werden.“

Die Software DDS-CAD zeichnet sich durch ihren intelligenten BIM-/CAD-Kern aus, der auch die Basis für DDS-CAD Security bildet. Das neue Werkzeug ermöglicht die flexible Installationsplanung für die Sicherheitstechnik nach modernsten Standards in 2D und 3D. Zugeschnitten ist es auf die Projektierung von VdS-gerechten Brand-, Einbruchmelde- und Gefahrenanlagen sowie Videoüberwachung und Zutrittskontrollen. Die Planung von Lichtruf- und Sprechanlagen, Präsenz- und Bewegungsmeldern wird mit DDS-CAD Security ebenso fachgerecht abgedeckt. Anwender profitieren neben herstellerneutralen Artikeln von den zertifizierten TELENOT-Produkten in der DDS-CAD-Datenbank. Weitere Zusammenarbeit besteht mit dem Spezialisten für Brandmeldeanlagen HEKATRON. Im Bereich Präsenz- und Bewegungsmelder, Beleuchtung sowie Notleuchten sind die hochwer-tigen Produkte von Esylux verfügbar. Die Bauteile aller Hersteller sind inklusive ihrer genauen technischen Spezifikationen, Abbildungen und Symbole implementiert. Die Installationen können dadurch realistisch in 3D visualisiert und geprüft werden. Für die Erfassungsbereiche von Esylux gibt es spezielle Simulationsoptionen. Vielseitige DDS-CAD-Funktionen wie automatische Anlagenschemata, Stücklisten und Legenden, etagenübergreifende Kabelplanung oder die gewerkeübergreifende Kollisionsprüfung sorgen für Zeitersparnis und Planungssicherheit. Das erlaubt dem Planer der elektronischen Sicherheitstechnik eine normgerechte Projektierung sowie eine präzise und schnelle Dokumentation der geplanten Installationen.

Mehr Informationen zum kompletten Funktionsumfang von DDS-CAD Security erfahren Besucher der light+building vom DDS-Messeteam in Halle 8.0 auf Stand J71 sowie in Halle 9.1, Stand E18 oder unter www.dds-cad.de/dds-cad-security.