Collaboration par excellence

Example: Hasselt City Hall, Belgium — The building of the new municipal administration center in Hasselt, Belgium, demonstrates how seamless collaboration in building projects can minimize risks and save costs from the design phase all the way to commissioning.
A joint project of several brands of the Nemetschek Group.
Nemetschek brands involved: Allplan, GRAPHISOFT, Solibri

Pioneering planning and project execution with Open BIM

“The end-to-end use of BIM solutions constitutes genuine added value for all stakeholders in the building process
because it enables seamless and efficient collboration”

Steven Hendrickx, Head Architect in Hasselt

Large-scale, highly complex building projects in particular require ongoing, reliable and efficient coodination between all stakeholders – both internal and external – across disciplines and between companies. Therefore, in association with other market players, the Nemetschek Group is promoting the Open BIM data standard. This is a universal, collaborative approach to designing, constructing and operating buildings based on open standards and workflows It makes it possible for project stakeholders to collaborate, even if the type of software varies from user to user. The Industry Foundation Classes (IFC) interface has established itself as an open standard and is therefore of central significance.

Sharing and evaluating data throughout the entire product life cycle saves time and money and improves quality. The administration of data is key to this digital transformation, for it is only possible to take full advantage of the potential if each stakeholder can access the data that he or she needs at any given time. This begins with a realistic BIM building model, which is an essential prerequisite for a genuine 5D workflo. This model is no longer limited to just 3D construction data; it also includes data concerning the dimensions of time and costs.

Seamless collaboration exemplified by the Hasselt City Hall

Under the management of the architect team comprising Jaspers-Eyers, MASS Architects and Michel Janssen, a new municipal administration center is being built in Hasselt. The complex, consisting of a renovated building section and a new building, provides approx. 17,000 m2 for the city administration and social services as well as offices. The architects and their most important partners are using Open BIM software solutions for the entire construction process. Three Nemetschek solutions are being implemented for this project: Archicad from Graphisoft for the design and planning of the architects, Allplan Engineering for civil engineering, and the Solibri Model Checker for the BIM quality control carried out by the construction company.

From the beginning, all information concerning the building project is contained in the digital building model – from the draft to implementation – including all design details, desired materials, fire protection requirements, acoustic properties, insulation and building structures, and administration. This constitutes considerable added value for all stakeholders compared to the old standard model, which was purely 3D. Thus, this improvement ensures more than just seamless collaboration between all those involved. The complex project can be turned over to the municipality – the proud building owner – with the required quality, on time and within the specified budget.

Hasselt City Hall is groundbreaking – in terms of design, planning and project implementation.

Independent and yet consistent

Steven Hendrickx, the head architect in Hasselt, recognized four decisive factors with Open BIM over the course of the successful project:

  • Individual partners design their model with their preferred BIM software, and with their own templates. Outstanding collaboration is ensured, though, thanks to a common, uniform standard which is specified in advance.
  • The division of labor is defined at the beginning of the project. Data on statics, for instance, have an essential impact on the architecture and structural design. Data on heating, ventilation and air-conditioning, on the other hand, are also important but don’t generally flow directly into the architecture. These data, for example, can be sufficiently analyzed with the BIM solution for quality assurance from Solibri.
  • Design changes in one area don’t necessarily affect the plans of all the others involved in the project. The architecture and the building stage are inherently the most closely linked.
  • The expertise of the staff, i.e., extensive holistic knowledge of the various building disciplines, is also critical for the success of the project.

Two examples of the advantage of precise planning

In Hasselt, the construction company was commissioned with excavation, among other tasks. An assessment of the amount of sand that needed to be removed was done based on a cal culation using conventional 2D planning methods, which yielded a result of 800 cubic meters. The engineers used the Solibri Model Checker based on Open BIM and the data provided by the architects and arrived at a figue that was just half this amount, i.e., 400 cubic meters of sand. This shows how exact the work with Open BIM solutions can be.

The steel struts to be installed are another example: With the interface function IFC Exports from Allplan, it was possible to use the BIM model to automatically calculate which steel struts needed fieproofing. All it took was a mouse click to obtain precise results, right down to the running meter. In projects that don’t use Open BIM solutions, these calculations are made by manually entering the data from 2D drawings in Excel or some other software and then recalculating and evaluating the data for use in quotations and planning, a process that is susceptible to error and one that leaves a lot of room for interpretation. These errors often go undetected until the actual cost planning is already completed. In the case of the Hasselt City Hall,  it was possible to avoid such errors from the outset.

Converting to Open BIM pays off

As is the case with any change, it takes a certain amount of time for companies and employees to accept BIM as the norm. The best way, according to Steven Hendrickx, is to start out by planning smaller projects using BIM. The experience thereby gained will make it possible to complete successively larger BIM projects. The advantages of collaborating through Open BIM are obvious: The entire workflow is much simpler for all project stakeholders, and building projects are completed within time and cost budgets.

CONCLUSION

Consistent standards and open interfaces in par-ticular are essential for successful building projects. Stakeholders need solutions that can “work together” for all and any individual tasks being performed. Seamless collaboration between humans and machines: This is ensured with Open BIM, and backed by the brands of the Nemetschek Group.



Reference projects on this topic:

Nemetschek Vectorworks & Synchro Software Ltd. Join Forces to Support Open BIM

Companies View IFC as a Strong Interoperability Option for Users

Columbia, Md., April 15, 201 – Nemetschek Vectorworks, Inc. and Synchro Software Ltd. have joined forces to provide truly open and flexible collaboration between architectural modeling and construction planning BIM tools. Both companies are committed leaders to the proliferation of open BIM workflows in design and construction and work to improve the efficiency of the industry through the successful implementation of open standards-based data exchange. In addition, both companies support the Industry Foundation Classes (IFC) file format as an interoperability solution for their customers.

“We believe systems interoperability is as important as supporting 3D data in our 4D BIM for construction planning and scheduling solution,” said Tom Dengenis, CEO of Synchro Software Ltd. “Our support for IFC dates back to 2008. We decided back then for clear strategic reasons to focus on Vectorworks, the clear leader in IFC, to guide our import and synchronization capabilities. From the start, and to this day, we singularly focus on developing and testing our capabilities with Vectorworks as the authoring system.”

“A core tenet of Vectorworks is to provide designers with creative freedom, and interoperability is essential as those designers work with other collaborators to transform their creative visions to a built reality,” said Jeremy Powell, director of product marketing at Nemetschek Vectorworks, Inc. “We're excited to work with Synchro Software, a company that is clearly committed to supporting open standards for the benefit of all professionals involved in the design and construction process. We look forward to continued collaboration with Synchro in the future as we strengthen our partnership.”

One recent example of a large BIM project using Synchro and Vectorworks software is the construction of two metro subway stations in Sao Paulo, Brazil. The Consortium Heleno & Fonseca and the TIISA made use of BIM technology as a support for studies and planning of the stations Eucaliptos and Moema, both part of the expansion of line five of the Sao Paulo metro. Vectorworks Architect software was used for the generation of the BIM models of the stations and for accurate estimations of volumes and areas of different building elements of the 3D models. Synchro was used to associate the elements of the model to the schedule activities, as well as to generate the 4D analysis.

Some of the resulting benefits of the 4D analysis included more speed and accuracy in the generation of the studies of the construction schedule alternatives, greater versatility and speed in decision-making, the creation of informative presentations of the work for external stakeholders through short videos, and visualization of the structures and equipment in different phases of the project.

More information about this project can be found here: www.cadtec.com.br/news/bim4d_metrosp_en.html